Sava and Kolubara bridge 1.5 meters away from being connected – Surcin-Obrenovac section to be completed by January 5, 2020?
Source: Tanjug
Sunday, 05.05.2019.
15:22
Comments
Illustration (Photo: CHOTE BKK/shutterstock)
The bridge, which is being built by China Communications Construction Company, is 1,581 meters long and 29 meters wide. The span between the columns is 275 meters.
The works began on May 5, 2017, and, under the contract, the entire 17.6-km Surcin-Obrenovac section should be completed by January 5, 2020.
The works on the section are worth USD 233.67 million. The PE Roads of Serbia is the investor and the works are financed by the Government of Serbia.
The highway should have four main lanes and two pullouts, of the total width of 29 meters.
The section is divided into five sectors. In addition to the construction of the bridge, it entails an overpass across the Ostruznica-Batajnica railway, as well as two interchanges.
The Surcin-Obrenovac highway will enable the connecting of Corridors 11 and 10 through the bypass route around Belgrade at the Surcin interchange.
Companies:
China Communications Construction Company ltd Beograd
China Communications Construction Company Ltd China
JP Putevi Srbije Beograd
Tags:
China Communications Construction Company
CCCC
bridge
Surcin
Obrenovac
Corridor 11
Sava
Kolubara
Comments
Your comment
Most Important News
Full information is available only to commercial users-subscribers and it is necessary to log in.
Follow the news, tenders, grants, legal regulations and reports on our portal.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno,
uz konsultacije sa našim ekspertima.