RTB Bor has 1,200 surplus employees
Comments
(Photo: Kuznetcov_Konstantin/shutterstock.com)
– The plan is for around 1,200 workers to leave RTB with stimulative severance payments, which would reduce staff costs by nearly USD 15 million. However, Bor also needs to employ around 300 young and educated people to work with modern and highly demanding equipment – emphasized the general manager of the company, Blagoje Spaskovski.
According to him, RTB is currently short of USD 80 million for maintaining current liquidity, of which USD 50 million in order to buy copper concentrate, necessary for putting the smelting capacities into operation, directly from subcontractors, instead of dealers. The remaining USD 30 million are needed for the purchase of processed materials and spare parts.
The chairman of the company also emphasized that RTB didn't have the money and that it could be secured only through a change in the ownership structure, thereby alluding to privatization or arrival of a strategic partner.
– The continuation of the productions requires USD 23 million for the purchase of the necessary new equipment in the Majdanpek copper mine. Furthermore, the reserves at the Cerovo 1 copper mine and nearly depleted, and the opening of Cerovo 2 is therefore necessary. The documentation for this job has been prepared, and the land buyout process has also been initiated – Spaskovski pointed out.
As Novosti learns, all this is being done so that conditions would be met in near future for the opening of the third and the biggest mine in the area, to be called Cerovo Primarno.
– The most important fact is that we don't have around USD 350 million needed in the next two years for opening a mine in the Cerovo complex, increasing the production in Majdanpek and underground mines within RTB – Spaskovski says.
The production of 48,000 tons of copper, 842 kilograms of gold and 4.3 tons of silver, as well as the processing of around 164,000 tons of imported copper concentrate, necessary for putting the new smelter with the capacity of 400,000 tons a year into operation at full capacity, have all been planned for this year.
Tags:
RTB Bor
RTB Bor Group
RTB Bor Managing Board
Blagoje Spaskovski
copper concentrate
Majdanpek copper mine
copper
Cerovo 1 copper mine
Cerovo 2 copper mine
Cerovo copper mine
Cerovo
Cerovo Primarno mine
Cerovo Primarno
gold
silver
gold production
silver production
copper production
copper concentrate processing
RTB Bor employee surplus
Comments
Your comment
Most Important News
Full information is available only to commercial users-subscribers and it is necessary to log in.
Follow the news, tenders, grants, legal regulations and reports on our portal.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno,
uz konsultacije sa našim ekspertima.