Reconstruction of the Slavija Square starts June 15 - Fountain construction totaling EUR 1,8 m announced
Bids will be opened May 12. Parallel
with the tender for reconstruction of the Slavija Square and Bulevar
oslobodjenja, from Slavija to Autokomanda, the Directorate for construction
land and construction of Belgrade will announce public tender for fountain
construction. Deadline for completion the entire project is 155 days. So, if everything
runs smoothly around June 15, it should be completed around November 15.
Tender for supervision of the works has already been released and the second stage comprises eight companies, there of them being large international companies.
Reconstruction of Slavija and Bulevar oslobodjenja will be carried out day and night. Machines will operate until 10 in the evening, and if they want, contractors will be able to ask for a permit for night work and thus prevent possible delays.